The cloud is connected by cable, and nobody is ordering it in time

The cloud is connected by cable, and nobody is ordering it in time

Thu, 26th Nov 2026 (Today)
Prof. Maurizio Bragagni OBE
PROF. MAURIZIO BRAGAGNI OBE CEO Tratos UK Ltd

I make cables for a living. I started in Britain moving cable drums from factory to site, and today I help lead Tratos, a family cable group founded in 1966 with seven factories and customers in 36 countries. From the factory floor, the AI boom looks different from the way it looks on a conference stage.

The data centre industry measures progress in GPUs, megawatts and computing capacity. They all matter. But a new facility only works when it has a reliable grid connection, network connectivity and power distribution inside the building. Increasingly, these are the things that hold up delivery. AI may live in the cloud, but the cloud has an electricity cable attached to it.

The essential infrastructure

Fibre connects the whole data centre industry, inside the building and out. It lets servers, storage and networks talk to each other; without it, nothing works. The International Telecommunication Union (ITU) estimates that submarine cables carry around 99% of the world's internet traffic. Citing the International Cable Protection Committee, it reports more than 170 cable repairs worldwide in 2025, almost four a week. Yet connectivity still sits low on most data centre planning lists.

I see the pressure on fibre from the buyer's side too. This year, even at around US$14 per fibre-kilometre, our own factories have struggled to get optical fibre delivered. If an established cable maker is kept waiting, a data centre project that orders late will wait longer.

Power is just as essential. Every process needs it, yet the grid connection is often left late, along with the equipment and cabling that distribute power once it arrives. The result is impressive buildings that cannot operate for months, because the grid connection and power allocation are not ready.

A growing supply-chain problem

New data centres are already running into connectivity problems, and the next few years could make it worse. McKinsey estimates that data centres will need $6.7 trillion of investment worldwide by 2030. It puts about $1.3 trillion of that into power generation, transmission, cooling and electrical equipment: the physical layer my industry supplies. Unless developers give supply chain and connectivity a higher priority, disruption looks inevitable.

The pressure is already visible in Britain. Research by data centre infrastructure specialist Onnec, reported by TechRadar Pro, found that 77% of UK data centre operators were hitting critical bottlenecks in sourcing cabling for AI workloads. In the same research, 41% said cabling always or frequently delays AI capacity projects.

There is no quick fix when delays hit. Cable manufacturing has its own limits: raw materials, energy prices, factory capacity and competition from grid, renewable and telecom projects for the same production lines. Once a supply problem is flagged, it can take weeks or months to resolve, and every week lands on the completion date.

There is also a question of where cable is made. Britain has very few cable manufacturers left. Capacity close to the project shortens lead times and makes delivery dates easier to check. You cannot save a supply chain without a strategy.

The need for realism

Too often, procurement runs separately from technical design and the construction programme. That is where unrealistic connectivity targets are born. A new submarine cable is a project measured in years, from design to operation. A data centre's cabling is a smaller job, but the lesson holds: physical connectivity takes time to move from specification to reality. Many electrical components and cables have long lead times. If procurement is not managed from the first design meeting, delays become unavoidable.

Realism also means designing for what you can buy. Specify recognised standards that several factories can make, not one maker's proprietary design. Where the engineering allows, look at aluminium conductors for medium-voltage power: they ease the pressure on copper and can shorten lead times. We are proposing exactly this to British network operators today.

The questions to ask before agreeing a completion date

A data centre is only finished when it is fully connected. Before committing to a go-live date, ask your cable suppliers:

1.     Is the fibre and power cable you need actually available, or are the quoted lead times still estimates?

2.     Has factory capacity been allocated to your order?

3.     Have the raw materials, copper, aluminium and optical fibre, been secured?

4.     Where will it be made, and how far does it have to travel?

5.     Are there firm dates for production, dispatch and delivery?

Then ask the same of the grid connection:

1.     Are the connection and power capacity secured?

2.     Are any works or approvals still outstanding that could move the date?

3.     Will contractors, specialist installation teams and testing resources be available when needed?

4.     What is the fallback if something important is late?

If you are going to meet your deadlines, every supplier must show you a credible plan to deliver what you need, when you need it. As a supplier, I would rather be asked these questions on day one than on the day the building should open.

Order the cable when you order the chips

The cloud is now so central to how we work that it is easy to forget the physical infrastructure underneath it. I have spent my working life on that physical side, and it does not move at the speed of software. If the cable is not ordered, secured and scheduled with the same urgency as the GPUs, no project can be confident of going live on time.